Design, Manufacturing, Erection and Commissioning of Enamel And CWC Pipe Coating Plant
1. Mechanical Scope of Supply
1.1. Design, fabrication and installation of local Packages:
· Conveyor System (applicable to 52 " pipe diameter).
· Pipe Racks.
· Melting and holding Kettle (5 &10 & 15 Tons).
· Oil Boilers (280° C operation Temp.).
· Overhead cranes (20 & 40 Tons).
· Cage fixing unit. (Including of Rotator table)
· Water pump station .
· Air pipeline.
1.2. Installation of foreign packages:
· Blaster package
· Primer package
· Batching plant
· Power generator (two set 800 KVA)
· Air compressor (two set)
· Cage welding and fixing unit ( Zublin Machine)
2. Electrical Scope of Supply
· Design, Procurement and installation of main electrical panels (HV, MV)
· Design, Procurement and installation of all equipment electrical panels.
· Design, Procurement and installation of all cables, Accessories and cable tray.
3. Civil Works
· Construction of all foundation for all package
· Construction of main power room
· Construction of water pool
· Preparation of bare / coated pipe storage area 200/000 m2